News

Construction to Begin Soon on Lake Weir Middle School Replacement

Construction to Begin Soon on Lake Weir Middle School Replacement

Work will begin very soon on the Lake Weir Middle replacement, as the Marion County Public School board unanimously approved the construction management contract for the guaranteed maximum price at their Oct. 28, 2025 meeting. Photo: Saga Communications/352today


OCALA, FL (352today.com) – The Marion County Public School Board unanimously approved the construction management contract for the guaranteed maximum price for the new middle school “DD,” Lake Weir Middle School Project, at their meeting Oct. 28.

The guaranteed maximum price for the Lake Weir Middle School replacement cost is $62,698,806.77. When the school district borrowed the certificate of participation for schools, the school district put $65 million in for this particular project, said Angela Usher, Marion County Public School senior director, operations.

“I’m very pleased the cost is $62 million, and the cost is coming in less at what was proposed $410 a square foot, it came in at $402 a square foot, which is great,” said Usher.

Breaking ground

The substantial completion date is scheduled for May 2027, with work starting in November 2025, but there may be a slight delay. The general area is about 152,000 square feet. The construction manager is Skanska. The architect is Harvard Jolly PBK.

“We do have some concerns about our permit and breaking ground. In talking with the contractor, he was hoping to start in November, so we can have an opening in 2027,” said Usher. “We’re still on track to do this, and even if it’s pushed back a couple of months, we can still make our opening date.”

Adding up the numbersĀ 

School Board member Dist. 5, Dr. Sarah James had concerns regarding the conditions, and when she was reviewing the GMP document, and totaling up the staff, the budget for the staff is listed as $3,132,144.40. There seemed to be a discrepancy in the numbers, as when she totaled the figures the amount came to $3,150,353.92. It may be clerical error, but Dr. James’s concern was that the GMP the board was approving in terms of the general conditions for the number that is indicated on Page 14 of the document, isn’t an accurate number based on what was being presented.

Pages 13 and 14 of the GMP document outline two pages of general conditions, which total $5.39 million, said James. However, the contract is only indicating general conditions for $3.1 million, and that was another area where James had concern.

“And finally, I do believe the cost for staff, being at $3.15 million for a school that’s coming in at this price, is significantly higher than schools we have seen completion recently, including Winding Oaks and Ross Prairie,” said James. “Those are my concerns… My question would be for the attorney about the legality of the number being inaccurate on page two item 2.4, entitled general conditions, and it not being reflective of the actual mathematical number that’s on page 14.”

School District Attorney Jeremy Powers told the school board, if the number is inaccurate, it would have to be amended.

“The amendment at this point appears to duplicate another inaccuracy,” said Powers. “If we amend something with an inaccuracy, we then have to amend it with a corrective action at a future point.”

If the discrepancy is the contractor’s mistake, the school district will benefit from it because it will incur the lower of the two costs, said Usher.

“I’ve been talking to the contractor, and they realize that they made a mistake it’s a minor amount, and they will honor the lower amount,” said Usher.

James’s concern is the total for pages 13 and 14 of the document, with the amount being $5.39 million, believing that’s what the school district is responsible for general conditions, yet 2.4 only says $3.13 million, and even if that is the total, it’s still significantly higher for the other projects that were recently completed.

“It’s not about the number of staff, it’s about the cost of the staff,” said James.

Winding Oaks was a $48 million GMP and they spent a little bit less than $2 million staff, said James, regarding the disparity.

“This is only $14 million more for a project and we’re spending essentially a million dollars more, so proportionately, it doesn’t seem to track for me,” said James.

On the general conditions, there are two categories. Staff is $3.1 million, said Usher. Then, there is general requirements, which is $2.3 million, so when added together, the total general condition is $5.39 million. When comparing the GMP of a middle school to an elementary school it incorporates not only the general conditions, but all the other special needs versus that of an elementary school. The time frame for the general conditions for staff is almost twice as long for staff for an elementary school.

Capitol concernsĀ 

However, the federal government shutdown is causing a delay in the process.

“In order for us to break ground, on that middle school, we have to have a letter from the U.S. Fish and Wildlife Administration, and it has to have two signatures, we’re waiting on both of them, one in Jacksonville and one in Atlanta, and then the government has to reopen, before that can even start,” said Dr. Allison Campbell, School Board Dist. no.1. “Once we get both of those signatures, a 30-day window happens, we pay a fine, and then we can break ground. It’s something that we’re hoping to get our congressmen and senators involved with, but there’s nothing that they can do at this juncture, until the federal government reopens for there to be staff to do the things that I just indicated.”

News

32 minutes ago in Entertainment

What to Stream: ‘Freakier Friday,’ NF, ‘Landman,’ ‘Palm Royale’ and Black Ops 7

Fresh

Jamie Lee Curtis and Lindsay Lohan re-teaming as the body-swapping mother and daughter duo in "Freakier Friday" and albums from 5 Seconds of Summer and the rapper NF are some of the new television, films, music and games headed to a device near you.

35 minutes ago in National

Supreme Court rejects call to overturn its decision legalizing same-sex marriage nationwide

Fresh

The Supreme Court on Monday rejected a call to overturn its landmark decision that legalized same-sex marriage nationwide.

37 minutes ago in Entertainment, Music

A look at the Rock & Roll Hall of Fame 2025 inductees and how they were honored

Fresh

The ceremony held Saturday at Los Angeles' Peacock Theater was a mix of tributes, speeches and performances by acts like Soundgarden, Salt-N-Pepa and Big Boi of Outkast, along with numerous A-list musical guests.

1 hour ago in Sports

Rodgers’ struggles continue to mount in Steelers’ loss to Chargers

Fresh

Aaron Rodgers' tenure with the Pittsburgh Steelers began on a high note with four wins in five games to start the season. Since then, however, the 41-year-old quarterback's performance has gotten progressively worse and worse as the Steelers have lost three of four.

1 hour ago in Sports

MLB pitchers Emmanuel Clase and Luis Ortiz charged with taking bribes to rig pitches for bettors

Fresh

Cleveland Guardians pitchers Emmanuel Clase and Luis Ortiz have been indicted on charges they took bribes from sports bettors to throw certain types of pitches, including tossing balls in the dirt instead of strikes, to ensure successful bets.

1 hour ago in Entertainment

Black hat worn by the Wicked Witch of the West in ‘The Wizard of Oz’ is going up for auction

Fresh

Just in time for the theatrical release of "Wicked: For Good," fans will get a chance to own memorabilia from the 1939 original film, "The Wizard of Oz," and one item is especially witchy.

1 hour ago in National, Trending

Flight cancellations and delays worsen as government shutdown drags on

Fresh

The pain Americans are facing at airports across the country is expected to get worse this week if Congress is unable to reach a deal to reopen the federal government.